A public inquiry into Essex's land buys for the Army and Navy junction and Sandon Park and Ride opens at County Hall on 24 November. Five objections stand.
A public inquiry into Essex County Council’s plans to buy land for the Army and Navy junction rebuild opens at County Hall on Tuesday 24 November.
The council needs the land to build its new hamburger roundabout and to expand Sandon Park and Ride. Where owners will not sell, it has made compulsory purchase orders. The Secretary of State for Transport must confirm them before the land can be taken.
An inspector will hear the case from 10am on the fourth floor of County Hall, Market Road. The government gave notice of the inquiry in the Essex Chronicle on 12 November.
What the inquiry covers
Three orders will be heard together:
- the Army and Navy Junction side roads order, which lets the council alter, stop up and build roads around the junction
- the Army and Navy compulsory purchase order, for the junction land
- the Sandon Park and Ride compulsory purchase order, for the car park expansion
The notice says the orders are needed for the junction improvement, the Sandon expansion, new walking and cycling routes and bus infrastructure.
Five objections
The council set out its case in two statements served on 26 August. At that date, five objections were still outstanding.
For the junction, the Army and Navy statement of case lists four. Three are from landowners or occupiers with a legal interest in the land. The fourth is a non-statutory objection, from people with no legal interest in the land.
The points raised include:
- land records: one set of objectors says the council’s land registration is inaccurate
- mitigation land: the same objectors question why fields are being taken for environmental mitigation
- speed limits: a request for 40mph on both carriageways of the A1114 Essex Yeomanry Way, rather than the 50mph stretch planned, partly because of traffic noise
- a business car park: one business objects to an easement over 13 spaces at the edge of its car park on the A1060 Parkway, needed to build a retaining wall
The council answers each point in the statement. On the speed limit, it says the A1114 is a dual carriageway now under the national limit of 70mph. It argues that 40mph would frustrate drivers, lead to speeding and push traffic onto other routes.
On the business, it says reasonable access must be kept during opening hours as a condition of the building contract. It also says that business had recently been in touch “seeking to finalise negotiations”.
For Sandon, the park and ride statement of case lists one objection. The owner of part of the existing car park already leases it to the county council until 2039. The owner says buying the freehold takes more than the council needs.
The council says it is pursuing compulsory purchase as “a fall back” because its funding comes with deadlines. It says it will keep negotiating with every landowner. Objections withdrawn before 24 November will not be heard.
What is being built
The junction carries about 70,000 vehicles a day and 70 buses an hour at peak times, according to the statement. It recorded 30 collisions between 2020 and 2024, five of them serious.
The council’s statements describe:
- a hamburger roundabout, with a road through the middle
- a speed limit of 40mph through the junction, 30mph on Baddow Road, and 50mph on part of the A1114 east to Maldon Road
- an environmental barrier beside Meadgate Terrace and Tusser Court
- about 1,800 spaces at Sandon Park and Ride, a net gain of about 380, including 129 for electric vehicles
- a new terminal building and a larger bus lay-by off the A1060 Maldon Road
No homes need to be bought, according to the Essex Highways scheme page. Most of the private land is farmland or commercial land.
Who pays
The package costs about £81 million.
The Department for Transport has committed £68.75 million. That money depends on the council securing the land, getting a valid tender and winning approval for a full business case.
Essex County Council is putting in £8.13 million. Chelmsford City Council is adding £4.0 million from its Community Infrastructure Levy, and about £54,000 comes from section 106 planning contributions.
The statement confirms the Chelmer Valley Park and Ride expansion has been dropped because costs have risen. The land stays safeguarded for later.
What it means for you
- Nothing changes on the roads yet. Essex Highways says construction “is scheduled to start in 2028 and is expected to be completed in 2031”, subject to final funding approval.
- You can read the papers. The orders and plans are at County Hall, Chelmsford Library and Great Baddow Library, and on the scheme page. The council’s evidence went online from 3 November.
- You may be able to speak. The inspector must hear the objectors and anyone with an interest in the land. Others can be heard at the inspector’s discretion.
The inspector reports to the Secretary of State, who decides whether to confirm the orders. No date has been given for that decision.
Frequently asked questions
When is the Army and Navy public inquiry?
It opens at 10am on Tuesday 24 November 2026 on the fourth floor of County Hall, Market Road, Chelmsford. An inspector appointed by the Secretary of State for Transport will run it.
Can anyone speak at the Army and Navy inquiry?
The inspector must hear the remaining objectors and anyone with an interest in the land. Other people may be heard at the inspector’s discretion, according to the government’s notice.
When will work start on the Army and Navy roundabout?
Essex Highways says construction is scheduled to start in 2028 and be completed in 2031, subject to final funding approval and other agreements.
Have your say